MISO-J3780
200 MW storage in Buchanan, IA · In queue since April 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3780 is a proposed 200 MW battery storage project located in Buchanan County, Iowa. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 18, 2024. The proposed commercial operation date is June 30, 2028. The interconnecting utility is ITC Midwest.
The project, sponsored by an unknown developer, consists solely of battery storage. As of the current data, the project's interconnection agreement (IA) status is unknown. The point of interconnection (POI) is Hazleton. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
IA
County
Buchanan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Hazleton
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTW.HZLT3.MVP
- POI Substation
- Hazleton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3780