Project MISO-J3784 — Project Summary

Queue ID
MISO-J3784
Capacity
200 MW
Technology
Battery
Status
active
Location
Ozaukee, WI
Region
MISO
Developer
IA Status

MISO-J3784

MISO-J3784BetaActiveBatteryMISOLBNL + Live

200 MW storage in Ozaukee, WI · In queue since April 2024 · Proposed COD June 2028

200 MW

Capacity

1

Components

Battery

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 2m

Pre-Study0%
Queue EntryApr 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

About

MISO-J3784 is a proposed 200 MW battery storage project located in Ozaukee County, Wisconsin. The project, which is in the MISO interconnection queue, was entered on April 18, 2024, with a proposed commercial operation date of June 30, 2028. The interconnecting utility is American Transmission Company.

The development project consists solely of battery storage, with a total capacity of 200 MW. The point of interconnection is the Saukville (Cedarsauk) substation.

Generated from interconnection queue and public data sources

Project Details

State

WI

County

Ozaukee

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Service Type

Point of Interconnection

Saukville (Cedarsauk)

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3784