MISO-J3784
200 MW storage in Ozaukee, WI · In queue since April 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3784 is a proposed 200 MW battery storage project located in Ozaukee County, Wisconsin. The project, which is in the MISO interconnection queue, was entered on April 18, 2024, with a proposed commercial operation date of June 30, 2028. The interconnecting utility is American Transmission Company.
The development project consists solely of battery storage, with a total capacity of 200 MW. The point of interconnection is the Saukville (Cedarsauk) substation.
Generated from interconnection queue and public data sources
State
WI
County
Ozaukee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Saukville (Cedarsauk)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.