MISO-J3785
200 MW storage in Kenosha, MI · In queue since April 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3785 is a proposed 200 MW battery storage project located in Kenosha County, Michigan. The project is interconnected within the Midcontinent Independent System Operator (MISO) queue, with an entry date of April 18, 2024. The proposed commercial operation date is June 30, 2028.
The project, which is under review by the American Transmission Company, consists entirely of battery storage. It is currently listed as active in the MISO interconnection queue. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
MI
County
Kenosha
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Pleasant Prairie
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Pleasant Prairie Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3785