MISO-J3787
247 MW generation in Stutsman, ND · In queue since April 2024 · Proposed COD June 2028
247 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3787 is a proposed solar generation project with a total capacity of 247 MW. The project is located in Stutsman County, North Dakota, and is being developed within the Midcontinent Independent System Operator (MISO) region. Otter Tail Power Company is the interconnecting utility.
The project entered the MISO interconnection queue on April 16, 2024, with a proposed commercial operation date of June 30, 2028. The point of interconnection (POI) is the Jamestown 345 kV Substation. As of the current data, the project's interconnection agreement (IA) status is not specified.
Generated from interconnection queue and public data sources
State
ND
County
Stutsman
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Jamestown 345 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- OTP.JAMSPK1
- POI Substation
- Jamestown Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.