MISO-J3792
125 MW generation in Gratiot, MI · In queue since April 2024 · Proposed COD April 2028
125 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
MISO-J3792 is a proposed solar generation project located in Gratiot County, Michigan, with a total capacity of 125 MW. The project, under consideration in the Midcontinent Independent System Operator (MISO) interconnection queue, was entered on April 18, 2024. The proposed commercial operation date is April 1, 2028. The point of interconnection is the Alma-Vestaburg 138kV line.
The project is currently listed as active in the MISO queue. The developer is unknown.
Generated from interconnection queue and public data sources
State
MI
County
Gratiot
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
ALMA - VESTABURG 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.