Project MISO-J3792 — Project Summary

Queue ID
MISO-J3792
Capacity
125 MW
Technology
Solar
Status
active
Location
Gratiot, MI
Region
MISO
Developer
IA Status

MISO-J3792

MISO-J3792BetaActiveSolarMISOLBNL + Live

125 MW generation in Gratiot, MI · In queue since April 2024 · Proposed COD April 2028

125 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4 years

Pre-Study0%
Queue EntryApr 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

About

MISO-J3792 is a proposed solar generation project located in Gratiot County, Michigan, with a total capacity of 125 MW. The project, under consideration in the Midcontinent Independent System Operator (MISO) interconnection queue, was entered on April 18, 2024. The proposed commercial operation date is April 1, 2028. The point of interconnection is the Alma-Vestaburg 138kV line.

The project is currently listed as active in the MISO queue. The developer is unknown.

Generated from interconnection queue and public data sources

Project Details

State

MI

County

Gratiot

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

METC

Entity

MISO

Service Type

Point of Interconnection

ALMA - VESTABURG 138.0kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MICHIGAN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.