Project MISO-J3801 — Project Summary

Queue ID
MISO-J3801
Capacity
195.64 MW
Technology
Solar
Status
active
Location
Mercer, IL
Region
MISO
Developer
IA Status

MISO-J3801

MISO-J3801BetaActiveSolarMISOLBNL + Live

195.64 MW generation in Mercer, IL · In queue since April 2024 · Proposed COD March 2028

195.64 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

3y 11m

Pre-Study0%
Queue EntryApr 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-31

About

MISO-J3801 is a proposed solar generation project located in Mercer County, Illinois, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 195.64 MW, is being developed by MidAmerican Energy Co. It consists of 195.64 MW of solar photovoltaic generation.

The project entered the MISO interconnection queue on April 18, 2024, and has a proposed commercial operation date of March 31, 2028. The point of interconnection is the Oak Grove - Sandburg (AMRN) 345.0kV line. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

IL

County

Mercer

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

MIDAMERICAN ENERGY CO.

Entity

MISO

Service Type

Point of Interconnection

OAK GROVE - SANDBURG (AMRN) 345.0kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ILLINOIS.HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
AMIL.IP.AZ
POI Substation
Sandburg

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3801