40 MW generation in Shelby, IL · In queue since June 2024 · Proposed COD March 2028
40 MW
Capacity
1
Components
Solar
1y 11m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
MISO-J3818 is a proposed 40 MW solar generation project located in Shelby County, Illinois. The project is interconnected within the Midcontinent Independent System Operator (MISO) queue, having entered the queue on June 7, 2024. The proposed commercial operation date is March 1, 2028. The interconnecting utility is Ameren Illinois.
The project, which is currently listed as active in the MISO queue, consists of 40 MW of solar photovoltaic generation. The point of interconnection (POI) is at the 4PANA 1 - 4SHELBYVL E 138.0kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Shelby
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
4PANA 1 - 4SHELBYVL E 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.