MISO-J3827
160 MW generation in Mackinac, MI · In queue since April 2024 · Proposed COD November 2028
160 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
MISO-J3827 is a proposed 160 MW solar generation project located in Mackinac County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 18, 2024. The proposed commercial operation date is November 1, 2028. American Transmission Company is the utility associated with the point of interconnection at the Indian Lake - Hiawatha 138.0kV substation.
The development project consists solely of solar photovoltaic generation, with a total capacity of 160 MW. The project's interconnection status is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Mackinac
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Indian Lake - Hiawatha 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3827