MISO-J3830
225 MW generation in IL · In queue since April 2024 · Proposed COD June 2028
225 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
MISO-J3830 is a proposed 225 MW wind generation project located in Illinois within the Ameren Illinois service territory. The project entered the MISO interconnection queue on April 16, 2024, with a proposed commercial operation date of June 1, 2028.
The project, which consists solely of wind generation, is currently listed as active in the MISO queue. The point of interconnection is designated as LRTP.
Generated from interconnection queue and public data sources
State
IL
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
LRTP
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3830