MISO-J3833
200 MW generation in Cass, ND · In queue since October 2024 · Proposed COD September 2028
200 MW
Capacity
1
Components
Wind
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3833 is a proposed 200 MW wind generation project located in Cass County, North Dakota. The project is being developed by Otter Tail Power Company and interconnected within the Midcontinent Independent System Operator (MISO) region. The project entered the MISO interconnection queue on October 1, 2024, with a proposed commercial operation date of September 1, 2028.
The interconnection point of the project is the Buffalo 115 kV substation. As of the latest data, the project's interconnection agreement status is not specified.
Generated from interconnection queue and public data sources
State
ND
County
Cass
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Buffalo 115 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Buffalo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.