MISO-J3834
300 MW storage in Gibson, IN · In queue since September 2024 · Proposed COD October 2026
300 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
MISO-J3834 is a proposed 300 MW battery storage project located in Gibson County, Indiana. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 19, 2024. Duke Energy Indiana is the utility associated with the project.
The proposed commercial operation date for MISO-J3834 is October 1, 2026. The point of interconnection is the Gibson Station - Francisco 345.0kV. As of the latest data, the project's interconnection status is active.
Generated from interconnection queue and public data sources
State
IN
County
Gibson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Gibson Sta - Francisco 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Francisco
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3834