MISO-J3837
200 MW generation in Van Buren, MI · In queue since December 2024 · Proposed COD June 2029
200 MW
Capacity
1
Components
Solar
1y 5m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
MISO-J3837 is a proposed 200 MW solar generation project located in Van Buren County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on December 2, 2024, with a proposed commercial operation date of June 1, 2029. The interconnecting utility is METC.
The proposed project consists of 200 MW of solar photovoltaic generation. It is currently in the active phase of the interconnection process within MISO. The point of interconnection is the ARGENTA - PALISADES 345.0kV substation.
Generated from interconnection queue and public data sources
State
MI
County
Van Buren
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
ARGENTA - PALISADES 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.