MISO-J3843
300 MW generation in Saginaw, MI · In queue since November 2024 · Proposed COD November 2027
300 MW
Capacity
1
Components
Solar
1y 6m
In Queue
—
IA Status
COD target: 2027
Total Duration
3 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-01
MISO-J3843 is a proposed solar generation project located in Saginaw County, Michigan, with a total capacity of 300 MW. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on November 21, 2024. The proposed commercial operation date is November 1, 2027.
The project, sponsored by Michigan Electric Transmission Company (METC), is currently in the active stage of the interconnection process within MISO. The point of interconnection (POI) is at the GOSS - SLATE 345.0kV substation.
Generated from interconnection queue and public data sources
State
MI
County
Saginaw
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
GOSS - SLATE 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3843