MISO-J3857
105 MW generation in — · In queue since December 2024 · Proposed COD April 2030
105 MW
Capacity
1
Components
Solar
1y 5m
In Queue
—
IA Status
COD target: 2030
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-04-01
MISO-J3857 is a proposed solar generation project with a total capacity of 105 MW. The project is located within the Midcontinent Independent System Operator (MISO) region. It entered the MISO interconnection queue on December 26, 2024, with a proposed commercial operation date of April 1, 2030. The point of interconnection is at the ALCONA - WHITTEMORE 138.0kV substation.
The project is sponsored by METC and is currently listed as active in the interconnection queue. No information is available regarding its location by county or state, its developer, its interconnection agreement status, or any news coverage. The project does not appear to be linked to an existing operating plant.
Generated from interconnection queue and public data sources
State
—
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
ALCONA - WHITTEMORE 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3857