MISO-J3858
110 MW generation in Livingston, MI · In queue since December 2024 · Proposed COD June 2029
110 MW
Capacity
1
Components
Solar
1y 5m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
MISO-J3858 is a proposed solar generation project with a total capacity of 110 MW, located in Livingston County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on December 18, 2024. The proposed commercial operation date is June 1, 2029.
The project, interconnected with ITC, consists of 110 MW of solar photovoltaic generation. It is currently listed as active in the MISO queue. The point of interconnection is the Madrid Substation 120 kV, bus number 265650.
Generated from interconnection queue and public data sources
State
MI
County
Livingston
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Madrid Substation 120 kV - Bus number 265650
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation