MISO-J3859
200 MW generation in Branch, MI · In queue since December 2024 · Proposed COD October 2028
200 MW
Capacity
1
Components
Solar
1y 5m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
The proposed MISO-J3859 project is a 200 MW solar generation project located in Branch County, Michigan. The project, developed by GridUnity, entered the MISO interconnection queue on December 17, 2024, with a proposed commercial operation date of October 1, 2028.
The project is currently listed as active in the interconnection queue. No Interconnection Agreement (IA) status is available.
Generated from interconnection queue and public data sources
State
MI
County
Branch
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GridUnity
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3859