MISO-J3865
250 MW generation in Shiawassee, MI · In queue since December 2024 · Proposed COD November 2028
250 MW
Capacity
1
Components
Wind
1y 5m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
The proposed MISO-J3865 project is a 250 MW wind generation facility located in Shiawassee County, Michigan. The project was entered into the MISO interconnection queue on December 8, 2024, with a proposed commercial operation date of November 1, 2028. The interconnecting utility is METC.
The project, sponsored by an unknown developer, is currently listed as active in the MISO queue. The point of interconnection is the CORNELL - LAYTON 138.0kV line. There is no record of an interconnection agreement (IA) for this project in the provided data, nor is there any indication of a match to an existing operating plant or recent news coverage.
Generated from interconnection queue and public data sources
State
MI
County
Shiawassee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
CORNELL - LAYTON 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3865