Project MISO-J3866 — Project Summary

Queue ID
MISO-J3866
Capacity
300 MW
Technology
Wind
Status
active
Location
Lapeer, MI
Region
MISO
Developer
IA Status

MISO-J3866

MISO-J3866BetaActiveWindMISOLBNL + Live

300 MW generation in Lapeer, MI · In queue since December 2024 · Proposed COD November 2028

300 MW

Capacity

1

Components

Wind

1y 5m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

3y 11m

Pre-Study0%
Queue EntryDec 6, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-11-01

About

MISO-J3866 is a proposed 300 MW wind energy project located in Lapeer County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on December 6, 2024, with a proposed commercial operation date of November 1, 2028. The interconnecting utility is ITC.

The project consists of 300 MW of wind generation. As of the latest data, the project is listed as active in the MISO queue.

Generated from interconnection queue and public data sources

Project Details

State

MI

County

Lapeer

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ITC

Entity

MISO

Service Type

Point of Interconnection

BENNET - GREENWOOD 120.0kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MICHIGAN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3866