MISO-J3870
87 MW generation in Vigo, IN · In queue since December 2024 · Proposed COD January 2024
87 MW
Capacity
1
Components
Gas
1y 5m
In Queue
—
IA Status
COD target: 2024
Total Duration
1y 5m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-01-26
MISO-J3870 is a proposed 87 MW gas-fired generation project located in Vigo County, Indiana. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on December 23, 2024. Duke Energy Indiana is the listed utility.
The proposed commercial operation date for MISO-J3870 is January 26, 2024. The point of interconnection is Sugar Creek.
Generated from interconnection queue and public data sources
State
IN
County
Vigo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
SUGAR CREEK
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sugar Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3870