MISO-J3883
250 MW storage in Crawford, IL · In queue since February 2025
250 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3883 is a proposed 250 MW battery storage project located in Crawford County, Illinois. The project, which is in the Ameren Illinois service area, is interconnected within the Midcontinent Independent System Operator (MISO) queue. The queue entry date is February 10, 2025. The project is currently in Phase 1 study phase and has NRIS service type.
The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Crawford
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
4HUTSONVL - 4HEATH 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.