MISO-J3886
300 MW generation in Swift, MN · In queue since February 2025
300 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3886 is a proposed 300 MW wind generation project located in Swift County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of February 11, 2025. The proposed point of interconnection (POI) is the Big Stone South - Alexandria 345kV line.
The project's interconnection service type is Network Resource Interconnection Service (NRIS), and it is currently in Phase 1 of the study process. The project's status is listed as active.
Generated from interconnection queue and public data sources
State
MN
County
Swift
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
Big Stone South - Alexandria 345kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Alexandria
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.