Project MISO-J3888 — Project Summary

Queue ID
MISO-J3888
Capacity
150 MW
Technology
Solar
Status
active
Location
Union, AR
Region
MISO
Developer
IA Status

MISO-J3888

MISO-J3888BetaActiveSolarMISOLive · MISO

150 MW generation in Union, AR · In queue since February 2025

150 MW

Capacity

0

Components

1y 3m

In Queue

IA Status

Interconnection

Total Duration

1y 3m

Study Phase

Phase 1

Pre-Study0%
Queue EntryFeb 6, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

MISO-J3888 is a proposed solar generation project with a total capacity of 150 MW, located in Union County, Arkansas. The project is being developed within the Entergy Arkansas service area and is interconnected to the EL DORADO EHV - SAREPTA 345/115 SS 345.0kV point of interconnection.

The project is currently active in the MISO interconnection queue, having entered the queue on February 6, 2025. It is undergoing a NRIS (Network Resource Interconnection Service) study and is currently in Phase 1 of the study process.

Generated from interconnection queue and public data sources

Project Details

State

AR

County

Union

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ENTERGY ARKANSAS, LLC

Entity

MISO

Service Type

NRIS

Point of Interconnection

EL DORADO EHV - SAREPTA 345/115 SS 345.0kV

Data Source

Live · MISO

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ARKANSAS.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3888