MISO-J3898
155 MW generation in Howard, IA · In queue since February 2025
155 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3898 is a proposed 155 MW wind generation project located in Howard County, Iowa. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on February 14, 2025. The proposed point of interconnection is at the MITCHELL COUNTY (ITCM) - HAZLETON (ITCM) 345.0kV line. The project's service type is Network Resource Interconnection Service (NRIS) and is currently in Phase 1 of the study phase.
The interconnecting utility for MISO-J3898 is ITC MIDWEST. The project is listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
IA
County
Howard
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
NRIS
Point of Interconnection
MITCHELL COUNTY (ITCM) - HAZLETON (ITCM) 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.