MISO-J3907
200 MW generation in Stark, IL · In queue since March 2025
200 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3907 is a proposed 200 MW hybrid generation project located in Stark County, Illinois. The project is interconnected to the Ameren Illinois utility and is listed in the MISO interconnection queue with a queue entry date of March 11, 2025. The point of interconnection is at the 4BUREAU - 4EKEWANEE N 138.0kV substation.
The project's interconnection service type is NRIS (Network Resource Interconnection Service). It is currently in Phase 1 of the study phase process within the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
Stark
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
4BUREAU - 4EKEWANEE N 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3907