MISO-J3908
196 MW generation in St. Joseph, MI · In queue since March 2025
196 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3908 is a proposed 196 MW solar generation project located in St. Joseph County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on March 10, 2025. The interconnecting utility is METC, and the designated point of interconnection (POI) is the Batavia-Morrow 138 kV line. The project's service type is Network Resource Interconnection Service (NRIS).
The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
St. Joseph
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
BATAVIA - MORROW 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3908