MISO-J3911
250 MW generation in Louisa, IA · In queue since February 2025
250 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3911 is a proposed 250 MW solar generation project located in Louisa County, Iowa. The project is sponsored by MidAmerican Energy Co. and is currently active in the MISO interconnection queue, with a queue entry date of February 25, 2025. The designated point of interconnection is SUB 93 LOUISA - SUB T HASKINS 345.0kV.
The project is undergoing a NRIS (Network Resource Interconnection Service) study and is currently in Phase 1.
Generated from interconnection queue and public data sources
State
IA
County
Louisa
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
NRIS
Point of Interconnection
SUB 93 LOUISA - SUB T HASKINS 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sub T
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.