MISO-J3918
138.38 MW generation in Champaign, IL · In queue since February 2025
138.38 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed MISO-J3918 project is a 138.38 MW wind generation facility located in Champaign County, Illinois. Interconnecting to Ameren Illinois via the 4RANTOUL - 4RISING 138.0kV point of interconnection, the project entered the MISO queue on February 6, 2025, and is currently in Phase 1 study phase. It is seeking NRIS (Network Resource Interconnection Service).
The project is listed as active within the MISO interconnection queue. No developer is specified in the queue data. The proposed project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
IL
County
Champaign
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
4RANTOUL - 4RISING 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.