MISO-J3923
1,414 MW generation in Washtenaw, MI · In queue since February 2025
1,414 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3923 is a proposed 1414 MW gas-fired generation project located in Washtenaw County, Michigan. The project, interconnected to the ITC utility via the Majestic-Milan 345 kV Line, entered the MISO interconnection queue on February 28, 2025, seeking NRIS service. It is currently in Phase 1 of the interconnection study process.
The project is listed as active in the MISO queue. The developer is unknown.
Generated from interconnection queue and public data sources
State
MI
County
Washtenaw
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Majestic-Milan 345 kV Line
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3923