MISO-J3924
80 MW storage in Branch, MI · In queue since March 2025
80 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3924 is a proposed 80 MW battery storage project located in Branch County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of March 5, 2025. The designated utility is METC, and the project's point of interconnection (POI) is the Coldwater - Moore Road 138.0kV substation. The service type requested is NRIS (Network Resource Interconnection Service).
The project is currently listed as active in the MISO queue. No information is available regarding a proposed commercial operation date or interconnection agreement status.
Generated from interconnection queue and public data sources
State
MI
County
Branch
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
COLDWATER - MOORE ROAD 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.