Project MISO-J3926 — Project Summary

Queue ID
MISO-J3926
Capacity
170 MW
Technology
Wind
Status
active
Location
Webster, IA
Region
MISO
Developer
IA Status

MISO-J3926

MISO-J3926BetaActiveWindMISOLive · MISO

170 MW generation in Webster, IA · In queue since March 2025

170 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Study Phase

Phase 1

Pre-Study0%
Queue EntryMar 13, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

MISO-J3926 is a proposed 170 MW wind generation project located in Webster County, Iowa. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 13, 2025. MidAmerican Energy Co. is the utility associated with the project.

The proposed project's point of interconnection (POI) is the Grimes - Lehigh 345kV line. The project is currently in Phase 1 of the study phase and is seeking Network Resource Interconnection Service (NRIS). The project's status is listed as active.

Generated from interconnection queue and public data sources

Project Details

State

IA

County

Webster

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

MIDAMERICAN ENERGY CO.

Entity

MISO

Service Type

NRIS

Point of Interconnection

Grimes - Lehigh 345kV

Data Source

Live · MISO

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3926