MISO-J3929
250 MW generation in Audrain, MO · In queue since January 2025
250 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
Total Duration
1y 4m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3929 is a proposed 250 MW wind generation project located in Audrain County, Missouri. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of January 31, 2025. Ameren Missouri is listed as the utility. The project's point of interconnection (POI) is Spencer Creek, and it is currently in Phase 1 of the interconnection study process.
The project is seeking Network Resource Interconnection Service (NRIS). As of the latest data, the project remains active in the MISO queue.
Generated from interconnection queue and public data sources
State
MO
County
Audrain
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
NRIS
Point of Interconnection
SPENCER CREEK
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- AMMO.AUDRN11
- POI Substation
- Spencer Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3929