MISO-J3935
975.4 MW generation in Genesee, MI · In queue since February 2025
975.4 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3935 is a proposed 975.4 MW gas-fired generation project located in Genesee County, Michigan. The project is being developed within the Midcontinent Independent System Operator (MISO) region and is listed in the MISO interconnection queue under queue ID J3935. The project, with utility METC, entered the queue on February 28, 2025, and is currently in Phase 1 study phase for Network Resource Interconnection Service (NRIS).
The project is listed as active in the interconnection queue. The point of interconnection (POI) is THETFORD.
Generated from interconnection queue and public data sources
State
MI
County
Genesee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
THETFORD
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CONS.GENESEESO
- POI Substation
- Thetford Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3935