MISO-J3936
133 MW generation in Kenosha, WI · In queue since February 2025
133 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3936 is a proposed 133 MW gas-fired generation project located in Kenosha County, Wisconsin. The project is in the MISO interconnection queue, having entered the queue on February 12, 2025. The point of interconnection is the Paris 345kV Substation. The project's service type is NRIS (Network Resource Interconnection Service) and is currently in Phase 1 of the study phase.
The American Transmission Company is the utility associated with the interconnection. The project is listed as active in the queue.
Generated from interconnection queue and public data sources
State
WI
County
Kenosha
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
PARIS 345kV Substation
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Paris Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3936