MISO-J3960
300 MW generation in Lac qui Parle, MN · In queue since April 2025
300 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3960 is a proposed 300 MW wind generation project located in Lac qui Parle County, Minnesota. The project is being developed within the Midcontinent Independent System Operator (MISO) region and is interconnected with Otter Tail Power Company at the Big Stone South - Deuel County 345.0kV point of interconnection. The project entered the MISO interconnection queue on April 8, 2025, and is currently in Phase 1 of the study phase.
The proposed project is designated as a Network Resource Interconnection Service (NRIS). Its status is currently listed as active within the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
MN
County
Lac qui Parle
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Big Stone South - Deuel County 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- South
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3960