MISO-J3962
165 MW generation in Bay, MI · In queue since March 2025
165 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3962 is a proposed 165 MW hybrid generation project located in Bay County, Michigan. The project, which falls within the Midcontinent Independent System Operator (MISO) region, entered the MISO interconnection queue on March 12, 2025. The interconnecting utility is METC.
The project is listed as "active" in the queue and is designated as a hybrid technology. The point of interconnection (POI) is the Bauer - Hampton 1 345.0kV line. The service type requested is NRIS (Network Resource Interconnection Service).
Generated from interconnection queue and public data sources
State
MI
County
Bay
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
BAUER - HAMPTON 1 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.