MISO-J3963
490 MW generation in Brookings, SD · In queue since April 2025
490 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed MISO-J3963 project is a 490 MW solar generation project located in Brookings County, South Dakota. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of April 7, 2025. Northern States Power Company is listed as the utility.
The project's interconnection service type is Network Resource Interconnection Service (NRIS) and its study phase is Phase 1. The project's status is currently listed as active.
Generated from interconnection queue and public data sources
State
SD
County
Brookings
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
BROOKINGS COUNTY
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Brookings County Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.