MISO-J3966
318 MW generation in Huron, MI · In queue since April 2025
318 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J3966 is a proposed wind generation project with a total capacity of 318 MW located in Huron County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 1, 2025. The point of interconnection is GRASSMERE, and the requested service type is NRIS.
The project is currently listed as active in the MISO queue. The transmission utility is ITC.
Generated from interconnection queue and public data sources
State
MI
County
Huron
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
NRIS
Point of Interconnection
GRASSMERE
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Grassmere Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.