MISO-J3978
200 MW generation in Sullivan, IN · In queue since April 2025
200 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed MISO-J3978 project is a 200 MW hybrid generation project located in Sullivan County, Indiana. Interconnecting to the Petersburg - Sullivan (AEP/PJM) 345.0kV point of interconnection, the project entered the MISO interconnection queue on April 8, 2025, under queue ID MISO-J3978. Duke Energy Indiana, LLC is the interconnecting utility.
The project's interconnection service type is NRIS (Network Resource Interconnection Service), and it is currently in Phase 1 of the study phase. The project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
IN
County
Sullivan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA, LLC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Petersburg - Sullivan (AEP/PJM) 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3978