Project MISO-J3999 — Project Summary

Queue ID
MISO-J3999
Capacity
1540 MW
Technology
Gas
Status
active
Location
Vermillion, IN
Region
MISO
Developer
IA Status

MISO-J3999

MISO-J3999BetaActiveGasMISOLive · MISO

1,540 MW generation in Vermillion, IN · In queue since April 2025

1,540 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection

Total Duration

1y 1m

Study Phase

Phase 1

Pre-Study0%
Queue EntryApr 14, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

MISO-J3999 is a proposed 1540 MW gas-fired generation project located in Vermillion County, Indiana. The project, which is in the Midcontinent Independent System Operator (MISO) interconnection queue, is being developed by Duke Energy Indiana, LLC. It entered the queue on April 14, 2025, with a service type of NRIS and is currently in Phase 1 of the study phase. The point of interconnection is the Sugar Creek - Cayuga CT 345.0kV substation.

The project is listed as active in the MISO queue.

Generated from interconnection queue and public data sources

Project Details

State

IN

County

Vermillion

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

DUKE ENERGY INDIANA, LLC

Entity

MISO

Service Type

NRIS

Point of Interconnection

Sugar Creek - Cayuga CT 345.0kV

Data Source

Live · MISO

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
INDIANA.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3999