MISO-J4000
343 MW generation in Scott, IL · In queue since April 2025
343 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4000 is a proposed solar generation project located in Scott County, Illinois, with a total capacity of 343 MW. The project is in the MISO interconnection queue, having entered on April 29, 2025. Ameren Transmission Company of Illinois is the utility associated with the project.
The project's interconnection service type is NRIS (Network Resource Interconnection Service). As of the latest data, the project's status is active and it is in Phase 1 of the study phase. The point of interconnection (POI) is the 7MEREDOSIA - 7TURNER 345.0kV line.
Generated from interconnection queue and public data sources
State
IL
County
Scott
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
7MEREDOSIA - 7TURNER 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.