MISO-J4002
200 MW storage in Edgar, IL · In queue since April 2025
200 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4002 is a proposed 200 MW battery storage project located in Edgar County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 30, 2025. The project's service type is NRIS (Network Resource Interconnection Service) and it is currently in Phase 1 of the study phase. The interconnecting utility is Ameren Transmission Company of Illinois.
The project's point of interconnection (POI) is at the 7KANSAS - 08SUGCRK 345.0kV substation. The developer is not specified in the queue data. The project has appeared in recent news coverage regarding MISO's interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Edgar
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
7KANSAS - 08SUGCRK 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.