MISO-J4007
150 MW generation in Peoria, IL · In queue since May 2025
150 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4007 is a proposed 150 MW wind generation project located in Peoria County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of May 15, 2025. The proposed point of interconnection is the 7FARGO - 7SANDBURG 345.0kV line, and the requested service type is NRIS (Network Resource Interconnection Service). The project is currently in Phase 1 of the study phase.
The project is within the service territory of Ameren Transmission Company of Illinois. As of the latest data, the project's status is listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
Peoria
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
7FARGO - 7SANDBURG 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.