MISO-J4009
80 MW generation in Marshall, MN · In queue since April 2025
80 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4009 is a proposed 80 MW solar generation project located in Marshall County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 25, 2025. Otter Tail Power Company is the interconnecting utility. The project's point of interconnection (POI) is the Viking - Karlstad 115.0kV substation. The project is currently in Phase 1 of the interconnection study process and is seeking Network Resource Interconnection Service (NRIS).
The project is listed as active in the MISO queue. No proposed commercial operation date or interconnection agreement (IA) status is available. There is no indication of an EIA match to an existing operating plant, nor is there any record of recent news coverage.
Generated from interconnection queue and public data sources
State
MN
County
Marshall
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Viking - Karlstad 115.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.