MISO-J4012
300 MW generation in Crittenden, AR · In queue since May 2025
300 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4012 is a proposed 300 MW hybrid generation project located in Crittenden County, Arkansas. The project, which is in the Entergy Arkansas service area, entered the MISO interconnection queue on May 15, 2025. Its point of interconnection is the Twist - Parkin 161.0kV substation.
The project's interconnection service type is NRIS (Network Resource Interconnection Service), and it is currently in Phase 1 of the study phase. The project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
AR
County
Crittenden
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS, LLC
Entity
MISO
Service Type
NRIS
Point of Interconnection
TWIST - PARKIN 161.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4012