MISO-J4016
300 MW storage in Tuscola, MI · In queue since May 2025
300 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4016 is a proposed 300 MW battery storage project located in Tuscola County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of May 20, 2025. The proposed project's point of interconnection (POI) is at the Atlanta-Thetford [Karn] 138 kV substation, and it is seeking Network Resource Interconnection Service (NRIS).
The project is currently listed as active in the interconnection queue. The transmission utility is ITC.
Generated from interconnection queue and public data sources
State
MI
County
Tuscola
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
NRIS
Point of Interconnection
ATLANTA - THETFORD [KARN] 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4016