MISO-J4018
250 MW generation in Ford, IL · In queue since May 2025
250 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4018 is a proposed 250 MW wind generation project located in Ford County, Illinois. The project is in the MISO interconnection queue, with an entry date of May 2, 2025. The proposed project, which is seeking NRIS service, is currently in Phase 1 of the study phase. The interconnecting utility is Ameren Illinois.
The project is listed as "active" in the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
Ford
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
Other_
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4018