MISO-J4019
200 MW storage in Calhoun, MI · In queue since May 2025
200 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4019 is a proposed 200 MW battery storage project located in Calhoun County, Michigan. The project, which is in the MISO interconnection queue, entered the queue on May 7, 2025. The designated point of interconnection (POI) is the Battle Creek - Oneida 345 kV substation. The project's service type is NRIS (Network Resource Interconnection Service).
The project is currently listed as active in the MISO queue. The listed utility is METC (Michigan Electric Transmission Company).
Generated from interconnection queue and public data sources
State
MI
County
Calhoun
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
BATTLE CREEK - ONEIDA 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4019