MISO-J4026
250 MW storage in Lenawee, MI · In queue since May 2025
250 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4026 is a proposed 250 MW battery storage project located in Lenawee County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of May 21, 2025. The point of interconnection is the BEECHER - KNOWLES 138.0kV substation. The project's service type is Network Resource Interconnection Service (NRIS).
The development project is currently listed as active in the MISO queue. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
MI
County
Lenawee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
BEECHER - KNOWLES 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.