MISO-J4029
85 MW generation in Mississippi, AR · In queue since June 2025
85 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
Total Duration
11 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4029 is a proposed 85 MW hybrid generation project located in Mississippi County, Arkansas. The project, which is interconnected to Entergy Arkansas, is listed in the MISO interconnection queue as of June 3, 2025. It is currently in Phase 1 of the study phase.
The project's point of interconnection (POI) is the Hybar 230kV substation. The service type requested is NRIS (Network Resource Interconnection Service). The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
AR
County
Mississippi
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS, LLC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Hybar 230kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.