MISO-J4031
245 MW generation in Scott, IL · In queue since May 2025
245 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4031 is a proposed solar generation project located in Scott County, Illinois, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 245 MW, is interconnected to the Ameren Transmission Company of Illinois via the 7MEREDOSIA - 7TURNER 345.0kV point of interconnection. It is currently in Phase 1 study phase of the MISO interconnection queue, with a queue entry date of May 12, 2025.
The project is listed as active in the MISO queue for Network Resource Interconnection Service (NRIS). No developer is specified in the queue data. The proposed project has appeared in recent news coverage regarding renewable energy development in the MISO region.
Generated from interconnection queue and public data sources
State
IL
County
Scott
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
NRIS
Point of Interconnection
7MEREDOSIA - 7TURNER 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.